Gutters Before or After the New Roof: Which Goes First

The order of gutter and roof work decides where the fascia gets opened, who touches the drip edge, and whether the trough is hung on sound wood.

If the roof and the gutters both need work in the same year, the order of the two jobs matters more than most quotes make it sound. A re-roof and a gutter replacement both work along the same edge of the house. They share the fascia board, the drip edge, the bottom course of shingles and the eave line where the trough sits. Whichever crew goes first will leave something for the other crew to work around, and a poor sequence can bend a new trough, pull a hanger or leave rotten fascia exposed for weeks. In St. Louis, where the freeze and thaw cycle works screws loose every winter, the sequence also decides how long an old trough hangs on soft wood before anyone replaces it.

Why the drip edge sets the order

The drip edge is a metal flange that runs along the rake and the eave under the shingles and bends out over the fascia. On many houses the back edge of the gutter tucks up under the bottom course of shingles or under that flange, so the two trades share a few inches of the same space. On a re-roof the old drip edge comes off during tear-off and a new one goes on. If the gutter is already hung, the roofer has to pull or work around the hanger screws and the back of the trough while the old shingles come off. A careful crew can do this without damage, but the risk is real, and it costs less to plan for it than to straighten a bent lip after the fact.

The question to settle is whether the drip edge will sit above or below the back edge of the gutter once everything is finished. Those are different details. If the drip edge sits above the trough, water runs over the metal and into the gutter. If the trough is set too low, the drip edge can carry water past the gutter instead. A written answer from the roofer and from the gutter installer, on the same sheet, keeps the two trades from each assuming the other one owns the overlap.

When the gutter goes first

Installing gutters before the new roof makes sense when the fascia is sound and the gutter can be fastened without disturbing the shingle layer. The gutter crew measures the outlets, sets the trough to the fascia and runs the downspouts down to grade. The roofing crew then tears off and works around a trough that is already in place. This order gives the gutter installer a stable eave to measure against, which helps when the old roof had a sagging edge.

The risk sits in the tear-off. Ask the roofer whether the crew will cover or protect the new trough, and whether they will keep shingle debris and nail heads out of the gutter. A tear-off drops a steady stream of old shingle grit and fasteners, and a trough full of that material will clog before the first heavy rain. Ask the roofer to clear the trough at the end of each roof day, and to say who does that work.

When the roof goes first

Re-roofing first is common, and it gives the gutter crew a clean, finished eave to measure. The roofer sets the new drip edge and the shingle courses, and the gutter crew then hangs the trough at the height the finished roof line sets. The catch is the old gutters. If they are still on the house during tear-off, they will collect shingle debris, nail heads and the occasional dropped bundle. Many crews take the old trough down before the roof starts, which leaves a stretch of open eave and fascia for a day or two, and longer if the weather turns.

That gap is the part to plan. Ask how many days the eave stays open, what covers the fascia during the gap, and what happens if rain arrives before the new trough goes up. A tarp or a temporary cover is a reasonable answer. A blank answer is not. A new roof can also change the height where the trough meets the shingle line, because a new starter course and a new drip edge add a little thickness at the eave. A gutter measured against the old roof should be checked against the finished eave before the trough is cut.

What the fascia decides

The fascia is the board the gutter hangs from, and it is the piece both orders depend on. A new gutter hung into rotten fascia will fail no matter which trade goes first, and a new roof laid over soft rafter tails or a failing fascia will leak at the edge. Before anyone sets a date, look at the fascia closely. Walk the eave from the ground with binoculars, then have the roofer or the gutter installer check it up close with a screwdriver. Soft wood, paint that blisters and bleeds water, and gaps at the corners all point to rot. Probe the bottom edge and the joint where the fascia meets the soffit. Use a stable ladder for this, or let the crew do the probing.

If the fascia needs repair, the repair belongs before the trough goes up. It is usually easier to do it between the roof and the gutter, while the old trough is off and the eave is open. A repair line on the bid should name the length of board, the material and whether the wood is replaced or only sistered. Treated lumber, primed and painted to match the rest of the eave, is a common answer on a St. Louis house, but the bid should say which one is intended.

Weather between the two trades

The St. Louis calendar sets much of this. Spring rain can soak the deck and the fascia for weeks, and a roof started in a wet stretch may wait for a dry day before the shingles go on. Late fall is harder. A gutter installed in late October and a roof started in November can leave an open eave into the first hard freeze. A trough hung on a wet fascia can also freeze to the wood before the sealant has cured. Ask each contractor what the cold limit is for their sealant and fasteners, and ask for the date the eave will be closed.

Hail season adds one more point. If the roof is being replaced after a storm, the gutters may already show dents on the trough and the downspouts. Photograph those before either trade starts, so the record of the damage exists before anyone touches the metal. Keys documents damage and puts a written scope with photos and measurements in the homeowner's hands, and the homeowner takes that to their own insurer. Missouri law, RSMo 407.725, forbids a roofing contractor from representing or negotiating a homeowner's insurance claim, so the photos belong with the homeowner from the start.

Permits and the desk you call

Many St. Louis County permit desks treat a roof permit and a gutter replacement as separate questions. Some towns want a roof permit with the scope written out, and some handle a gutter-only job with a simpler call or none at all. Ask the roofer which permit they will pull, whether the gutter work is listed on it, and which desk to call if the city wants the gutter work listed separately. The answer depends on the town, so get it from the desk rather than from memory.

Gutters and guards

If you are adding guards during this work, set them after the trough is hung and checked for pitch. A guard fastened to the trough is easier to inspect and replace than one tied into the shingle edge. Ask which trade installs the guard, and whether the guard lip will sit at the finished shingle edge without lifting the bottom course. A guard hung before the roof is done can be bent by the tear-off crew, so the guard order should follow the roof work rather than lead it.

What it costs

Sequencing changes the bill in a few places. A separate gutter visit before the roof adds a trip. A gutter reinstall after the roof adds a second round of hanger work if the old hangers come out during tear-off. A gap in the eave adds protection work, and a fascia repair adds wood and paint. Ask each contractor to price the gutter work as its own line, the roof work as its own line and any fascia repair as a unit price per foot, so the numbers can be compared without guessing what sits inside a combined total.

Also ask who hauls the old gutter, and who keeps the aluminum. An old trough that comes down during the roof job is scrap, and the contract should say whether the scrap goes to the crew or stays with the homeowner. That single line can move the total more than the per-foot rate does, and it is easy to miss when the two trades quote separately.

What to ask

  • Which trade goes first, and why that order fits the fascia you have.
  • Whether the old gutters stay on during tear-off or come down first, and how many days the eave stays open.
  • Whether the drip edge will sit above or below the back edge of the new trough, in writing.
  • Who inspects the fascia for rot before the trough is hung, and what a repair line costs per foot.
  • Whether the gutter height is checked against the finished eave after the new roof is on.
  • Who clears the trough of shingle grit at the end of each roof day, and who hauls the old gutter.

The Keys Roofing office number is (314) 220-2333. Ask for both trades to be written on one schedule before any date is set.

Ask about the two weeks

Book it before the leaves have finished falling

The check that matters most is the one almost nobody does: a hose down every downspout once the trees are bare, with somebody at the bottom watching where the water actually comes out.

If you would rather not be the person on the ladder for that, say so, and tell us how many storeys we are talking about.